Hempstead and Melody Resurfacing Project

Project Responsibility: Springfield Township

Construction Estimate: $974,025

Project Location: Hempstead and Melody

Description:

Complete rehabilitation of the road infrastructure.  The work will include installation of new concrete curb, construction of new catch basins, asphalt repairs to the subgrade, and resurfacing of both streets. 

Funding: This project is being funded through Township levy dollars (Approximately $487,012) and a SCIP (State Capital Improvement Program) Grant in the amount of $487,013.

Status: Currently the Township is evaluating the benefits of combining this capital improvement with Hamilton County’s Daly Road resurfacing project.  Hempstead Drive as well as Daly Road are contiguous and combining these projects could potentially provide significant savings on the overall cost for construction.

Contractor: TBD

Project Manager - Mike Gould, , 522-1410, mgould@springfieldtwp.org

Bid Award Date: TBD

Construction Start Date: Spring of 2017

Estimated Completed Date: Fall 2017


Correspondence to Residents:


Update Notes:


Updated 1/28/16