Hempstead and Melody Resurfacing Project

Hempstead and Melody Map
Project Responsibility: Springfield Township

Construction Estimate: $974,025

Project Location:
Hempstead and Melody

Description:
Complete rehabilitation of the road infrastructure. The work will include installation of new concrete curb, construction of new catch basins, asphalt repairs to the subgrade, and resurfacing of both streets.

Funding:
• Grant Funding From State Capital Improvement Program =$ 487,012
• Road Levy/Township General Fund = $487,012

Status: Phase 1 of this project (new curb installation) will be completed by July 31st. Phase 2 will consist of rebuilding all catch basins within the project area. The estimated completion date for phase 2 is August 31st.

Contractor: Ray Prus Construction

Project Manager - Mike Gould, 522-1410, mgould@springfieldtwp.org

Bid Award Date: February 2, 2017

Construction Start Date: June 1, 2017

Estimated Completion Date: Nov 1, 2017

Construction Estimated Timeline:
Project Schedule - Daly Road and Hempstead Drive


Phase 1
Curb replacement on Hempstead Drive
4/17/17
Phase 2
Curb replacement on Daly Road
6/10/17
Phase 3
Embankment repair on Daly
8/23/17
Phase 4
Removal of existing asphalt on Hempstead and Daly
9/1/17
Phase 5
Resurfacing of Hempstead Drive and Daly with new blacktop
10/1/17
Phase 6
Project completion
11/1/17

Correspondence:

Letter to residents announcing the project and expectations
3/20/17

Letter to residents announcing construction schedule 4/5/17

Letter to residents announcing early start to asphalt phase of construction 8/17/17

Update Notes:
Updated 8/2/17