Hempstead and Melody Resurfacing Project

Project Responsibility: Springfield Township

Construction Estimate: $855,486

Project Location: Hempstead and Melody

Description:

Complete rehabilitation of the road infrastructure.  The work will include installation of new concrete curb, construction of new catch basins, asphalt repairs to the subgrade, and resurfacing of both streets. 

Funding:
• Grant Funding From State Capital Improvement Program =$ 427,743
• Road Levy/Township General Fund = $427,743

Status: In order to save money as well as to minimize the negative impact to township residents during construction, this project was combined with the Daly Rd Resurfacing Project being performed by the Hamilton County Engineers.

Sewer replacement on the corner of Hempstead and Cottonwood was completed March 31, 2017.

Contractor: Ray Prus Construction - concrete work
John J Jurgenson Company will be subcontracted for the asphalt portion of the project

Project Manager - Mike Gould, 522-1410, mgould@springfieldtwp.org

Bid Award Date: February 2, 2017

Construction Estimated Timeline:

Project Schedule - Daly Road and Hempstead Drive
   
 Phase 1
Curb replacement on Hempstead Drive
4/17/17
 Phase 2
 Curb replacement on Daly Road
 6/10/17
 Phase 3
 Embankment repair on Daly
 8/23/17
 Phase 4
 Removal of existing asphalt on Hempstead and Daly
 9/1/17
 Phase 5
 Resurfacing of Hempstead Drive and Daly with new blacktop
 10/1/17
 Phase 6
 Project completion
 11/1/17

Correspondence:

Letter to residents announcing the project and expectations
  3/20/17

Letter to residents announcing construction schedule  4/5/17

Update Notes:
Updated 3/29/17



Contact Us

  1. Service Department
    Mike Gould, Director
    Email

    952 Compton Road
    Cincinnati, OH 45231

    Ph: 513-522-4004

    Staff Directory
Hempstead and Melody Map