Meredith Road Resurfacing Project

Project Responsibility: Hamilton County

Construction Estimate: $5,245,000

Project Location: Meredith Rd. from Hamilton Ave. to Daly Rd. 

Scope of Project:

Complete rehabilitation of the road infrastructure.  Construction will include installation of new concrete curb, storm sewers, removal of existing asphalt, and resurfacing with new blacktop. 

Funding Sources: This project is being funded through Hamilton County’s Road and Bridge Fund as well as a State Capital Improvement Grant.

Status:  Construction on this project started on January 23, 2017.

Project Manager: Ted Hubbard - Questions should be attention to Tim Gilday, (513) 946-8900  tim.gilday@hamilton-co.org

Bid Award Date: TBD

Construction Start Date: January 23, 2017

Estimated Completion Date: November 1, 2017

Project Notes:
Last updated 2/3/17