2017 Capital Improvement Overview

Project Name/Streets
Number of Lane Miles Being Resurfaced
Estimated Construction Cost
Completion Date
Work To Be Performed
Kempermill Village Resurfacing Project
Deerhorn, Fallbrook (west of Deerhorn), Fullerton (west of Deerhorn), & Forester (between Mill & Elkwood)
1.0 $722,844 7/1/17 This project is a complete rehabilitation of these roads, including new concrete curb, storm sewers, and asphalt surface.
Hempstead Drive and Melody Lane Resurfacing Project .78 $855,486 11/1/17 This project is a complete rehabilitation of both roads, including new concrete curb, storm sewers, and asphalt surface. 
Millbrook Resurfacing Project
Millbrook, Leebrook, Woodfield, Streambrook, Timbermill, Allencrest, Shadyoak, Galecrest, Thomasview, Viewcrest, & Ashford
2.07 $497,536 12/1/17 This project includes repairs to the concrete curb, storm sewers, and all roads being resurfaced with black mat or asphalt.
Wyoming Point Resurfacing Project
.21 $50,000 12/1/17 This project includes repairs to the concrete curb, storm sewers, and resurfacing of both roads with asphalt.
Golf View and Cambridge Acres Resurfacing Project
Acreview, Cheshire, Stargate, Silverbrook, & Silverglade
1.26 $145,125 12/1/17 This project includes repairs to the concrete curb, storm sewers and resurfacing all roads with black
Lakeshore Estates Resurfacing Project
Lochcrest, Whitestone, Winstead, Riddle, Stonehearst, Tipton, & Altaview
1.69 $182,175 12/1/17 This project includes repairs to the concrete curb, storm sewers and resurfacing of all roads with black mat. 
Storm Sewer Repairs
Various locations
N/A $100,000 12/15/17 This project includes replacement of deteriorated storm sewers throughout the Township
Catchbasin and Sidewalk Repair
Various locations
N/A $80,000 12/1/17 This project includes replacement of all sidewalk blocks that are deemed to be hazardous and catch basins rated  'poor' condition.  
TOTAL   $2,633,166