Hempstead and Melody Resurfacing Project

Hempstead and Melody Map
Project Responsibility: Springfield Township

Construction Estimate: $974,025

Project Location:
Hempstead and Melody

Complete rehabilitation of the road infrastructure. The work will include installation of new concrete curb, construction of new catch basins, asphalt repairs to the subgrade, and resurfacing of both streets.

• Grant Funding From State Capital Improvement Program =$ 487,012
• Road Levy/Township General Fund = $487,012

Status: Phase 1 of this project (new curb installation) will be completed by July 31st. Phase 2 will consist of rebuilding all catch basins within the project area. The estimated completion date for phase 2 is August 31st.

Contractor: Ray Prus Construction

Project Manager - Mike Gould, 522-1410, mgould@springfieldtwp.org

Bid Award Date: February 2, 2017

Construction Start Date: June 1, 2017

Estimated Completion Date: Nov 1, 2017

Construction Estimated Timeline:
Project Schedule - Daly Road and Hempstead Drive

Phase 1
Curb replacement on Hempstead Drive
Phase 2
Curb replacement on Daly Road
Phase 3
Embankment repair on Daly
Phase 4
Removal of existing asphalt on Hempstead and Daly
Phase 5
Resurfacing of Hempstead Drive and Daly with new blacktop
Phase 6
Project completion


Letter to residents announcing the project and expectations

Letter to residents announcing construction schedule 4/5/17

Letter to residents announcing early start to asphalt phase of construction 8/17/17

Update Notes:
Updated 8/2/17