Brookview Pavement Preservation Project

Project Responsibility: Springfield Township

Construction Estimate: $149,955.00

Property Assessment per Parcel: $74.22 per year for 10 years

Project Location: Meredith, Sherborn, Newcastle, and Westbury

Scope of Project: This pavement preservation project is intended to bring the streets inside Brookview Subdivision back to good condition again.  Construction will include full depth repairs to asphalt sub-grade, and resurfacing with new blacktop

Funding Sources: 

  • Springfield Township Road Levy and General Fund = $149,955.00
  • Property Assessment = $74,977.50 (after 10 years of collections)

Status: The Springfield Township Board of Trustees has awarded the contract for this project to Barrett Paving.  Construction is scheduled to start the in the beginning of October.       

Contractor: Barrett Paving

Project Manager: Mike Gould, 513-522-4004, mgould@springfieldtwp.org 

Bid Award Date: May 8, 2019

Construction Start Date:  Approximately October 1, 2018

Estimated Completion Date: Approximately December 1, 2018


Page Updated Aug 2, 2018