Greenpine Acres Resurfacing Project:
Project Responsibility: Springfield Township
Construction Estimate: $252,528.00
Property Assessment per Parcel: $82.80 per year for 10 years
Project Location: Greenpine, Springbeauty, Persimmon, Thistle
Scope of Project: This pavement preservation project is intended to bring the streets inside Greenpine Acres Subdivision back to good condition again. Construction will include repairs to concrete curb, storm sewers, some full depth as well as partial depth repairs to asphalt sub-grade, and resurfacing with new blacktop
Funding Sources:
- Springfield Township Road Levy and General Fund = $252,528.00
- Property Assessment = $101,016.00 (after 10 years of collections)
Status: The Springfield Township Board of Trustees awarded the contract for this project to Barrett Paving. Construction is scheduled to start the in the beginning of October.
Update: Project Completed
Contractor: Barrett Paving
Project Manager: Mike Gould, 513-522-4004, mgould@springfieldtwp.org
Bid Award Date: May 8, 2018
Construction Start Date: Approximately - October 1, 2018
Estimated Completion Date: December 1, 2018
Updated 10-11/19