2021 Springfield Township Resurfacing Program

Wildbrook Acres Project Map
Hollydale Project Map
Burlington Meadows Project Map
Project Responsibility: Springfield Township

Construction Estimate: $3,372,014.75

Property Assessment per Parcel: $58.55 per year for 10 years

Project Location:

Maria Avenue, Briarrose Court, Toulon Drive, Cloverton Court, Merrymaid Lane, Nohunta Court, Sherman Terrace, Sherwood Drive, West McKelvey, Wildbrook Lane, Terway Lane, Kelso Court, Lakeview Drive, Northfield Lane, Ridgebrook Court, Northbrook Court, Garnoa Drive, Sunwood Court, Crestbrook Drive, Southfield Court, Ferbrook Court, Belsage Court, Newgate Lane, Sarbrook Drive and Woodmill Lane.

Description:

This project is an extensive rehabilitation of the above 25 streets. Construction will include the installation of new concrete curb where there is currently existing curb, repairs to storm sewers as well as catch basins, significant full depth repairs to asphalt sub-grade, removal of existing asphalt which will allow for resurfacing with 2.5 inches of new blacktop.



Funding Sources:
    • State Capital Improvement Grant = $1,686,007.38
    • Township General Fund (JEDZ) = $1,079,044.72
    • Township Road Levy = $404,641.77
    • Property Assessment = $202,320.89 (after 10 years of collections)
Status: This project has reached its final phase.  Installation of new storm sewer on Lakeview & Maria Ave, final layer of asphalt on both streets, & restoration will occur this spring.         

Contractor: Adleta

Project Manager:
Mike Gould, 513-522-4004, mgould@springfieldtwp.org

Bid Award Date: April 13, 2021

Estimated Construction Start Date: June 1, 2021

Estimated Completed Date: July 1, 2022

Update Notes:

updated 3/25/22

 Maria Ave., Briarrose Ct., Toulon Dr., Cloverton Ct., Merrymaid Ln., Nohunta Ct., Sherman Terrace, Sherwood Dr., W. McKelvey, Wildbrook Ln., Terway Ln., Kelso Ct., Lakeview Dr., Northfield Ln., Ridgebrook Ct., Northbrook Ct., Garnoa Dr., Sunwood Ct., Crestbrook Dr., Southfield Ct., Ferbrook Ct., Belsage Ct., Newgate Ln., Sarbrook Dr., & Woodmill Ln. 

 Maria Ave., Briarrose Ct., Toulon Dr., Cloverton Ct., Merrymaid Ln., Nohunta Ct., Sherman Terrace, Sherwood Dr., W. McKelvey, Wildbrook Ln., Terway Ln., Kelso Ct., Lakeview Dr., Northfield Ln., Ridgebrook Ct., Northbrook Ct., Garnoa Dr., Sunwood Ct., Crestbrook Dr., Southfield Ct., Ferbrook Ct., Belsage Ct., Newgate Ln., Sarbrook Dr., & Woodmill Ln. 

 Maria Ave., Briarrose Ct., Toulon Dr., Cloverton Ct., Merrymaid Ln., Nohunta Ct., Sherman Terrace, Sherwood Dr., W. McKelvey, Wildbrook Ln., Terway Ln., Kelso Ct., Lakeview Dr., Northfield Ln., Ridgebrook Ct., Northbrook Ct., Garnoa Dr., Sunwood Ct., Crestbrook Dr., Southfield Ct., Ferbrook Ct., Belsage Ct., Newgate Ln., Sarbrook Dr., & Woodmill Ln. 

 This project is an extensive rehabilitation of these 25 streets. Construction will include the installation of new concrete curb(where there is currently existing curb), repairs to storm sewers as well as catch basins, significant full depth repairs to asphalt sub-grade, removal of existing asphalt which will allow for resurfacing with 2 . inches of new blacktop.